What should I do if I need more time to obtain a required permit (or permit modification) beyond the maximum time periods provided for in the eDisclosure system?

Regulated entities should make every effort to ensure their violations are corrected as expeditiously as practicable, within the maximum time periods provided for in the eDisclosure system. Where the correction of a violation requires the issuance or a modification of a permit, the disclosing entity may submit its compliance certification for purposes of eDisclosure if it has filed a complete permit application with the relevant regulatory agency, and permit issuance/modification is pending.